Schedule changes planned for Shore Line East

Associated Press

Publication: theday.com

Published 06/15/2012 12:00 AM
Updated 06/15/2012 07:04 AM

NEWINGTON, Conn. (AP) — The Connecticut Department of Transportation is making changes to the Shore Line East commuter train schedule now that a bridge project in Madison has been completed early.

Starting Monday, buses will no longer be needed to accommodate the River Road rail bridge project and most train service will return to pre-construction schedule times.

James Redeker, the DOT commissioner, said the state worked closely with Amtrak to finish the bridge project three weeks earlier than originally planned. Construction has taken about two months.

DOT plans to republish Shore Line East rail schedules on July 2.

Those schedules will include additional service to and from New London on Friday July 6th, Saturday July 7th and Sunday July 8th for the OpSail 2012 tall ships festival. At least 24 ships are expected.

Also of Interest

Town News

Visit Zip06
Submit Your:  Submit Your News Submit Your Photos Submit Your Events
Most Recent Poll
On Aug. 14 Connecticut Democrats and Republicans will choose their candidates for U.S. Senate and in several other races. Are you following the primary elections?
Yes, I’m keeping a close eye on these important races.
55%
No, it’s summer. Get back to me in the fall.
26%
There’s a primary election?
20%
Number of votes: 493

Have you spotted a celebrity?

Have you ever spotted any celebrities around the region? Tell us who, where and when via email to tips@theday.com. Include photos if possible.