New Morgan Moving Forward

New Morgan School Moving Forward: This is the latest drawing of the rear entrance of the new Morgan School. On the left are the cafeteria and kitchen on the lower level and the learning commons (media center and library) on the second level. Also shown on the left is the amphitheater for outdoor classes and lunches. This is the bus entrance for student drop off and leads to the auditorium on the left and the gymnasium on the right. Stairs leading to the offices and classrooms and foyer are also at that entrance.
New Morgan School Moving Forward: This is the latest drawing of the rear entrance of the new Morgan School. On the left are the cafeteria and kitchen on the lower level and the learning commons (media center and library) on the second level. Also shown on the left is the amphitheater for outdoor classes and lunches. This is the bus entrance for student drop off and leads to the auditorium on the left and the gymnasium on the right. Stairs leading to the offices and classrooms and foyer are also at that entrance. Image courtesy of Newman Architects PC of New Haven

In an effort to keep the public informed of the new Morgan project, The Morgan Building Committee will submit an article semi-monthly to the Harbor News. To suggest topics or request answers to questions, write to morganbuildingcmt@clintonct.net.

The Morgan Building Committee recently received the news that all of the state and federal permits necessary to move forward with the new Morgan project have been approved.

The process, which began four years ago, called for town, state, and federal applications and approvals, numerous meetings, engineering studies and reports, and architectural planning and designs, among the other requirements to get the final go-ahead to go out to bid.

According to Hal Chait of the project's construction manager, FIP Construction, Inc., "The construction schedule will commence in September of 2014 and be completed by May 2016."

The final bidding proposal has been put together by FIP Construction, Inc., which covers all facets of the building project, was published and distributed on
July 25, 2014.

It calls for potential subcontractors to submit their bids for work on the new Morgan project by Aug. 21.